Sr.No.Name of Procuring EntityBrief Description of Award (Start Date-End Date)Total Value (In Crores)Alloted To (Name of Agency)Date of Allotment
1 Bawal PHED (Tender No. 94719) PROVIDING CANAL BASED WATER SUPPLY SCHEME FOR 16 NO. VILLAGES, THE. and DISTT. REWARI. “Construction of water works at Kamalpur, IBS at Devlawas, 4 VBS at different villages comprising Design, Construction and Commissioning of 1.00 MLD and 1.50 MLD SCADA based water Treatment plants at Kamalpur { 15/10/2018 - 14/04/2020 } 6.88 Ram Avtar Gupta 04/10/2018
2 Bawal PHED Tender No. 100629) Providing independent based water supply scheme Raghunathpura group of 25 Nos. villages and 3 No. Dhanies District Rewari, “Design, Construction testing and commissioning of 3.50 MLD SCADA based Water Treatment Plant, construction of ra { 26/01/2019 - 25/06/2020 } 23.42 Rakesh Yadav 10/01/2019
3 Bawal PHED Master sewerage Scheme Dharuhera Town Distt. Rewari (ON RISK AND COST OF SH. RAJENDER CONTRACTOR R/O HOUSE NO. 5845, SHIVAJI NAGAR, TEH. and DISTT. GURUGRAM) { 01/04/2020 - 30/06/2020 } 5.14 Vinod Manocha, Contractor (3) 16/04/2018
4 Bawal PHED Ibrahimpur, providing canal based water works gr. of 17 No. villages { 01/11/2018 - 30/10/2019 } 11.7 Jai Shree Balaji Const Co. Panipat. 29/10/2018
5 Bawal PHED Khaleta, Providing water supply scheme for 14 Nos. villages and 1 No. Dhani { 07/12/2017 - 07/05/2019 } 17.85 M/s Shri Balaji Builders. house No. 858-P Sector 33 21/11/2017
6 Bhiwani PHED No. 1 Up gradation of existing sewege treatment plant of 20 MLD capacity ( 2 Nos x10 MLD each ) based on moving bed reactor (MBBR) technology to tertiary treatment plant located at Dhana Road in Bhiwani Town { 17/03/2021 - 16/09/2022 } 15 Rathee Construction Company 15/03/2021
7 Charkhi Dadri PHED Providing and laying HDPE rising main for treated effluent from existing 2 No. STP.s upto drain No. 8 Charkhi Dadri Const. of 1 No. Pump chamber, 1 No. collecting tank at jhajjar road STPs laying of 37700 mtr. { 15/09/2020 - 14/06/2021 } 31.74 Jain Irrigation Systems Limited 02/09/2020
8 Charkhi Dadri PHED Mehra:- Providing canal based water supply scheme form Mehra Group of 6 No. village constructing canal based water work a village mehra. { 25/03/2020 - 24/08/2021 } 7.92 Suresh Kumar, Contractor 13/03/2020
9 Charkhi Dadri PHED Providing canal ased water supply scheme for sirsali Group of 12 No. Village constructing canal based water works at village { 05/04/2020 - 04/10/2021 } 12.71 M/S MAHALAXMI CONSTRUCTION COMPANY 27/03/2020
10 Charkhi Dadri PHED Proc canal based water supply scheme avillage ninar badesara gr of 35 no. Villages , ` const of raw water pumping station at with intermediate bs at incl o and m of 5 years and all other works contingent thereto { 28/03/2021 - 27/09/2022 } 33.82 M/S MAHALAXMI CONSTRUCTION COMPANY 24/03/2021
11 Faridabad PHED No. 1 Detailed Project Report for Augmentation Water Supply Scheme at Village Tigaon (95) @155 LPCD Block Faridabad Constituency Tigaon Distt. Faridabad (Under Rural Augmentation) Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at Village Tigaon, Block Faridabad Tehsil and District Faridabad (Under Mahagram Yojna) Under CM Announcement. { 04/06/2019 - 03/12/2020 } 14.33 Mehta Construction co. M/s 04/06/2019
12 Fatehabad PHED Up-gradation and commissioning after conversion of existing 10 MLD capacity sewage treatment based on moving Bed BRT to combined activated sludge process in conjunction with MBBR Bio film process with, Anoxic Tank, Internal Recirculation Pumps, Treated effluent lifting pumps with tertiary treatment based on Deep Bed Filters followed by chlorination in existing STP complete in al respect { 09/10/2018 - 08/01/2020 } 5.59 Shree Balaji Builders 03/10/2018
13 Fatehabad PHED Augmentation of Water Supply Scheme and Construction of 2nd Water Works Village Gorakhpur Tehsil and . Design, Construction, Testing and commissioning of 1.00 MLD Water Treatment Plant at Old Water Works and 1 MLD Water Treatment Plant 2nd Water works Construction of Raw Water Pumping Station Near Fatehabad Branch at Jandli Kalan Road Gorakhpur { 21/08/2019 - 20/02/2021 } 6.09 Jai Shree Balaji Const Co. Panipat. 14/08/2019
14 Fatehabad PHED Aug. of canal based ww Bhuna Town “Const of inlet channel, ss tank, wtp fully automated with PLC/ SCADA system, rwp ump house, cwt, DGH sets and transformers at WW, raising and repair of boundary wall, supply erection, comm of pm, elect, mech piping instrumentation work and laying, jointing, cutting of DI rising main pipe line for Zone No. 1, 2, 3, 4, 5 and 6 of Bhuna town including OandM for 5 years after completion of 3 months trial run { 19/12/2017 - 18/03/2019 } 8.56 Maha laxmi Const. Company M/S 13/12/2017
15 Fatehabad PHED Pro Sew. Sch. Cons of STP for Bhuna Town of Distt Fatehabad ` Des. cons, erection, testing comm of automatic and PLC cont with SCADA 18MLD Main pump station, const of automatic and PLC controlled with SCADA 8.00 MLD STP based on sequential batch reactor (SBR) tech., including laying jointing, cutting and testing of 450 mm dia D.I., Pipe treated effluent rising main and pump chamber treated effluent Includ staff quarters, approach roadsand Others { 19/12/2017 - 18/06/2019 } 10.06 Aparna Const.Company M/S 13/12/2017
16 Gohana PHED No. 1 Tender No. 2019_HRY_80989_1-PART –A WATER SUPPLY AUGMENTATION WATER SUPPLY SYSTEM OF VILLAGE KHANPUR KALAN DISTT. SONIPAT { 23/08/2019 - 22/02/2021 } 7.09 Rohtash Kumar Contractor 13/08/2019
17 Gohana PHED No. 1 Tender No. 2019_HRY_80989_1- PART B SEWERAGE SYSTEM - PROVIDING SEWERAGE SYSTEM IN VILLAGE KHANPUR KALAN { 23/08/2019 - 22/02/2021 } 8.14 Rohtash Kumar Contractor 13/08/2019
18 Gohana PHED No. 1 TENDER NO. 2020_HRY_151667_1-BHAINSWAL KALAN-PROVIDING SEWERAGE SYSTEM (SEWAGE TREATMENT PLANT (STP)) IN VILLAGE BHAINSWAL KALAN DISTT. SONIPAT (NAME OF WORK AS PER DNIT ATTACHED) { 15/01/2021 - 14/07/2022 } 5.75 M/s. SFA and Associates 06/01/2021
19 Gohana PHED No. 1 Tender No. 2020_138952_1- (A) Water Supply - Providing Water Supply in Village Bhainswal Kalan Mithan and Bhainswal Kalan Bawla. (Name as per DNIT) { 01/09/2020 - 31/03/2022 } 7 Jai Shree Balaji Const Co. Panipat. 20/08/2020
20 Gohana PHED No. 1 Tender No. 2020_138952_1- (B) Providing Sewerage System in Village Bhainswal Kalan Mithan and Bhainswal Kalan Bawla (Name as per DNIT) { 01/09/2020 - 31/03/2022 } 10.05 Jai Shree Balaji Const Co. Panipat. 20/08/2020
21 Gohana PHED No. 1 Tender No. 2021_HRY_155623_1 - SHAMRI GROUP: DPR FOR PROVIDING RAW WATER TO EXISTING 3 W/W ie SHAMRI, CHIRANA and MUNDLANA FROM JLN CANAL, UPDATING OF EXISTING STRUCTURES OF W/W. CONSTRUCTION OF C/B WATER WORKS AT KAILANA KHAS FOR GROUP OF 3 VILLAGES, PROVIDING FHTC and LAYING OF BALANCE PIPE LINES IN VILLAGES DISTT. SONIPAT. (NAME OF WORK AS PER DNIT) { 01/04/2021 - 31/03/2022 } 7.6 Nafe Singh Contractor 22/03/2021
22 Gurugram PHED Construction of Inlet Channel, Hodies, RCC Sump well, Pump Chamber, Laying, Jointing and Testing of Raw Water rising main from 250 mm to 600 mm i/d D.I. K9 pipe from WW Iqbalpur to W/W Mushedpur, Birhera and Mehchana and Providing canal based water supply in adational 8 Nos. villages and also providing FHTC { 01/08/2021 - 31/01/2023 } 25.71 Narender Singh Contractor 23/06/2021
23 Gurugram PHED DNIT for `Designing, Constructing, Testing, Commissioning of Boundary Wall with iron gate 400 mtr, laying of 500 mm i/d D.I.- K9 Rising main, 100 mm to 450 mm i/d D.I. K7 internal distribution, including providing and fixing D.I.Spls. and reconstruction of streets with interloackingtiles complete in all respect and and all other works contingent there to and Operation and Maintenance for 5 year in village NaharpurKasan Haryana.`` { 15/07/2018 - 15/07/2019 } 7.09 Jain Construction Co. Hisar M/S 21/06/2018
24 Gurugram PHED DNIT for `Designing, Constructing, of Boundary Wall with iron gate 220 mtr, laying andTesting, Commissioning of 700 mm and 500 mm i/d D.I.-K9 Rising main, 100 mm to 450 mm i/d D.I. K7 internal distribution, including providing and fixing D.I.Spls. and reconstruction of streets with interlockingtiles complete in all respect and and all other works contingent there to and Operation and Maintenance at village Manesar { 15/07/2018 - 15/07/2019 } 17.04 Jain Construction Co. Hisar M/S 21/06/2018
25 Gurugram PHED Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 350mm, 400 mm, 450mm S.W. Pipe and 500 mm, 600 mm, 700 mm and 900 mm i/d RCC Np3 pipe sewer, construction of brick masonry manholes chambers and reconstruction of streets with interlocking tiles complete in all respect and and all other works contingent there to in village manesar { 15/07/2018 - 15/07/2019 } 17.04 Jain Construction Co. Hisar M/S 21/06/2018
26 Gurugram PHED Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 350mm, 400 mm, 450mm S.W. Pipe and 500 mm, 600 mm, 900 mm and 1200 mm i/d RCC Np3 pipe sewer, construction of brick masonary manholes chambers and reconstruction of streets with interloacking tiles complete in all respect and and all other works contingent there to in village Naharpur Kasan { 15/07/2018 - 15/07/2019 } 7.09 Jain Construction Co. Hisar M/S 21/06/2018
27 Hansi PHED Part -A : Kapro :- Upgradation of WS Scheme and Const. of 2nd WW Kapro Distt. Hisar ` Const. of 2 No. RCC FB, 2 Nos RCC CWT at 1st w/w, 400mm i/d RCC NP2 pipe IC, 2 No. B/L S/S Tank, 2 Nos. RCC S/S Well, 2.00MLD WTP, 2 No. RCC CWT, 1 No. PC, B/Wall etc. { 20/09/2019 - 19/03/2021 } 5.59 Bharat bhushan Contractor 19/09/2019
28 Hansi PHED Part – B : Kapro :- Providing sewerage facilities and sewerage treatment plant in village Kapro Distt. Hisar, “ Laying of Sewer line, construction of manhole and House sewer connection intercepting chamber for sewerage system in village Kapro Distt. Hisar and all other work contingent thereto { 20/09/2019 - 19/03/2021 } 8.65 Bharat bhushan Contractor 19/09/2019
29 Hansi PHED Petwar :- Upgradation of WS Sch. under Mahagram Yojna. ` Const. of RCC Open I/C, 2 No. RCC S/S Tank, 2 Nos. RCC S/S Well, 3.00 MLD WTP, 7 No. RCC CWT, 1 No. PC, B/Wall, 2 No. RCC UGC Tank at B/Stn. structures and installations, O and M of W/W for five years and all other works contingent thereto` { 08/11/2019 - 07/05/2021 } 10.94 Ravinder Sharma 06/11/2019
30 Hansi PHED Providing sewerage facilities and sewerage treatment plant in village Petwar, Distt. Hisar Under Mahagram Yojna, “Laying of sewerage , construction of manhole and House sewer connection intercepting chamber for sewerage system in village Petwarand all other works contingent thereto { 08/11/2019 - 07/05/2021 } 6.39 Ravinder Sharma 06/11/2019
31 Hansi PHED Hansi Town – Providing and laying of sewer line in balance streets of various colony Hansi Town CM Announcement `Laying of sewer line, construction of main hole, repair and raising of manhole and construction of IPS etc. and all other works contingent thereto { 24/04/2020 - 23/10/2021 } 6.34 M/S Sat Narain Gupta 20/04/2020
32 Hisar PHED No. 2 Barwala Town Estimate for Providing and laying HDPE Rising main for Treated Effluent from Existing STP to Proposed Pond Distt Hisar. Constt. of RCC Collecting tank, BM PC C.C. Road, Excavation of Pond, Const. of Brick Masonry BW, Laying of HDPE PN-4 PE-80 Rising Main from STP to Pond, Providing and Installation of Pumping Machinery with all accessories and all other works contingent thereto`. { 15/02/2021 - 15/02/2022 } 5.18 M/s. SFA and Associates 10/02/2021
33 Jhajjar PHED No. 3 Shyama Parsad Mukherji Rurban Mission (Badli Cluster) 17 Nos. villages, District Jhajjar, up-gradation of water supply schemes from 70 to 135 LPCD for 12 villages falls under PHED No. 3, Jhajjar, District Jhajjar { 01/10/2019 - 31/03/2021 } 6.75 Chahar Construction Co. 11/09/2019
34 Jind PHED No. 1 Up gradation and commissioning after conversion of existing 15 MLD capacity sewage treatment based on Moving Bed Biological Reactor Technology (Attached growth process) to combined activated sludge process in conjunction with MBBR Bio film process with addition of Anoxic Tank, Internal Recirculation Pumps, Treated Effluent Lifting Pumps with Tertiary Treatment. { 16/05/2018 - 15/08/2019 } 8.39 M/s Shiv Construction Company Jind 11/05/2018
35 Jind PHED No. 1 Providing and laying of 560 mm o/d HDPE Rising Main for sewerage from 5 MLD Existing STP (Ahirka) to Kalwa-Kinana Drain for Jind town Distt. Jind,`Design, Construction, Erection, Testing and Commissioning of 560 mm o/d HDPE rising main from 5 MLD Existing MLD to Kalwa-Kinana Drain etc. { 01/10/2019 - 30/09/2020 } 16 Jain Irrigation Systems Limited 18/09/2019
36 Jind PHED No. 1 Providing and laying of sewerline in newly approved colonies and construction of STP for Jind town { 24/11/2017 - 23/05/2019 } 11.12 The Dikadla Co.op.L/C Society Ltd.,Dikadla Tehsil Samalkha Distt. Panipat. 16/11/2017
37 Jind PHED No. 2 Muana:- Aug. Water Supply Scheme for village Muana under Mahagarm Yojna { 16/09/2019 - 15/03/2021 } 8.26 M/s COMPETENT BUILDERS AND CONTRACTORS 12/09/2019
38 Jind PHED No. 2 Muana:Prov. Sewerage System in Village Muana Distt. Jind { 16/09/2019 - 15/03/2021 } 10.71 M/s COMPETENT BUILDERS AND CONTRACTORS 12/09/2019
39 Kaithal PHED No. 1 Pai-Providing Sewerage System in village Pai Design, Const. erection testing and commissioning of MPS of 3.50 MLD with peak factor 2.5 and STP of 3.50 MLD based on SBR laying of 400 mm i/d HDPE pipe of length 1600 mtr for disposal of Treated Effluent from STP to drain including Room, CCTV cameras, Transformer, DG set independent feeder at STP including OandM of 12 months run of 3 months and 10 years { 21/06/2019 - 20/06/2020 } 5.85 U.B.A. Constructions 13/06/2019
40 Kaithal PHED No. 1 E-Tender No. 106911- Pai(Adarsh village) Revised estimate for Up-gradation of water supply Pai Tehsil Pundri District Kaithal “Design , testing commissioning of authomated PLC controlled SCADA based water purification plant of 1.00 MGD (4.54 MLD) capacity at 2nd water works Pai construction of 1 No. S/S Tank and 2 No. RCC Clear Water Tank working depth and supplying and installation of 2 Nos Horizontal split { 08/03/2019 - 07/03/2020 } 6.39 Rohtash Kumar Contractor 26/02/2019
41 Kaithal PHED No. 1 E-Tender No. 71803- Upgradation of Water Supply Scheme Pai District Kaithal “Laying , jointing , cutting and testing of DI distribution network of 100 mm to 500 mm and all other works contingent thereto and sewerage system in village Pai, “Supplying, laying, jointing and testing stone ware pipes of 100 mm to 400 mm and construction of brick masonary manhole chambers and SFRC manhole covers and frames and all other works contingent thereto.” { 27/04/2018 - 26/01/2019 } 9.42 Ashok Kumar Contractor 25/04/2018
42 Kaithal PHED No. 1 E-Tender No. 71803- Upgradation of Water Supply Scheme Pai District Kaithal “Laying , jointing , cutting and testing of DI distribution network of 100 mm to 500 mm and all other works contingent thereto and sewerage system in village Pai, “Supplying, laying, jointing and testing stone ware pipes of 100 mm to 400 mm and construction of brick masonary manhole chambers and SFRC manhole covers and frames and all other works contingent thereto.” { 27/04/2018 - 26/01/2019 } 9.42 Ashok Kumar Contractor 25/04/2018
43 Kaithal PHED No. 2 Siwan Detail Project Report for construction of Sewage Treatment Plant and Sewerage Network in village Siwan Tehsil Guhla and Distt Kaithal (Haryana) “Design, Construction, erection, testing and Commissioning of main pumping station of 4.50 MLD with peak factor 2.50 consisting of collecting tank with screening with chamber size, village Siwan Tehsil Guhla and District Kaithal Haryana. { 10/09/2019 - 09/09/2020 } 12.8 V.S.Enterprises 06/09/2019
44 Kaithal PHED No. 2 Construction of Sewerage Treatment Plant and Sewerage Network in village Siwan Tehsil Guhla Distt. Kaithal,” Supplying, Laying, Jointing and testing of stone ware pipes of 200mm to 400mm and 500mm to 600mm of RCC NP3 pipes and construction of Brick masonry Manhole chambers and SFRC Manhole covers and frames and all other works contingent thereto { 16/08/2017 - 15/05/2018 } 10.54 Rohtash Kumar Contractor 09/08/2017
45 Karnal PHED No. 1 NIGDHU-“Pro.and Inst.of 1 t/w of size 250mmx200mm upto 205 mtr. depth BGL, { 16/08/2019 - 15/08/2020 } 8.72 ANURAG GOEL 13/08/2019
46 Karnal PHED No. 2 Design, Construction, Erection, testing and commissioning of automatic and PLC controlled with SCADA 4 MLD STP maim pumping station, const. of automatic and PLC controlled with SCADA 4 MLD STP { 01/06/2018 - 30/11/2019 } 6.41 Jai Shree Balaji Const Co. Panipat. 01/06/2018
47 Karnal PHED No. 2 Up-gradation of water supply and providing sewerage system in village Kohand Block Gharaunda Distt. Karnal “Providing, Laying, Jointing, cutting and testing of Sewerage Network System of S.W. pipe size 200 mm dia, 250 mm dia, 300 mm dia, 400 mm dia and 500 mm dia, construction of manhole, Construction of interceptic chamber, making of household connections. Operation and maintenance of water supply scheme and Sewerage Network System { 18/09/2020 - 17/03/2022 } 6.1 M/s M.R Construction Company Kaithal 08/09/2020
48 Kosli PHED Detailed Project for upgradation of W/S system from 70 LPCD to 135 LPCD for 08 Nos. covered under SPMRM, ` Const. of 02 Nos. Inde. canal based W/W for village Bhakli and Chawwa including all required electrical and mechanical equipments. { 10/06/2020 - 09/12/2021 } 6.49 Rakesh Yadav 02/06/2020
49 Kurukshetra PHED Tender no.104789_1 Providing Sewerage network and construction of sewage treatment plant in ismailabad town { 28/11/2019 - 27/05/2021 } 9.55 Inderjeet Singh Contractor 13/11/2019
50 Mandi Dabwali PHED Providing and Laying of Sewerage System in Recently Approved Colonies at Mandi Dabwali Distt. Sirsa. Providing and laying of Sewer Lines i.e. 200mm, 250mm, 300mm dia S.W. pipe in recently approved colonies and 280mm o d Rising Main HDPE Pipe PE80 grade and PN4 from Proposed IPS to existing 16.50 MLD STP at Mandi Dabwali Town Distt. Sirsa { 21/09/2020 - 20/09/2021 } 5.19 MANGAT RAI 14/09/2020
51 Mandi Dabwali PHED Augmentation water supply scheme to Village Ganga Distt. Sirsa. Providing and laying of 700mm dia RCC Pipe Class NP-2 and construction of SS Tank 1 No., S/S Tank 1 No., RW Water Suction and CW Scour Tank, RCC High Level Tank 1 No., Filtration Plant - 2 MLD SCADA based - 1 No., RCC Clear Water Tank 3 No., Pump Chamber with RCC Column , Boundary Wall, Toilet Block 1 No., etc. and all other works contingent thereto { 19/08/2019 - 18/02/2021 } 7.99 M/s Balaji Construction Company 14/08/2019
52 Mandi Dabwali PHED Providing Sewerage System and construction of STP at Village Ganga Distt. Sirsa. Providing and laying of various sizes of Sewerage Lines and construction of manholes, 1 No. Collecting tank and screening chamber, inspection chamber, pump chamber, Boundary Wall with Iron Gate, Rising Main, Toilet Block, Staff Quarter, Instt. of pumping machinery and all required Electrical, Mechanical Equipment’s etc. at village Ganga. { 19/08/2019 - 18/02/2021 } 7.65 M/s Balaji Construction Company 14/08/2019
53 Mohindergarh PHED Satnali Village Aug. of Drinking W/s Scheme 25 Nos villages“Construction of 1 Raw water Pumping station, 1 water work, 4 IBS, 32 VBS at different villages comprising Design, Construction, Testing and Commissioning of 8.50 MLD SCADA based water Treatment plant, Balancing capacity reservoir, S and S Tanks, Clear waterTanks, Pump chambers, Boundary wall, R/W and C/W Rising main lines, Internal Distribution of 25 villages and 9 Dhanies. { 14/02/2019 - 13/02/2020 } 34.34 ANAND ENGINEERS 06/02/2019
54 Mohindergarh PHED Part-1 W/s- Aug. of drinkig w/s scheme for 25 Nos villages on Canal based . Part-2 Sewerage System Prov. sewerage system in village Satnali Distt. Mohindergarh (Under Swaran Jayanti Mahagram Yajna)`Laying of Sewerage network of various size of construction of Manholes in village Satnali OandM of 5 Years including defect liability period after trial run period of 3 Months and all other works contingent there to. { 17/01/2019 - 16/01/2020 } 7.61 Vikash Badesra Contt. 09/01/2019
55 Narnaul PHED No. 1 Design, construction, erection and commissioning of STP of Capacity 3.00 MLD on SBR technology, MPS of Capacity 9.00 MLD, laying of 600 mm i/d RCC NP-3 pipe treated effluent channel, construction of 1 No. Staff Quarter, boundary wall, CC Path, land scaping, MCC Panel Room, 5 Nos. CCTV Cameras, Electric Transformer, D.G. Set and all other contingent electrical, mechanical piping { 01/03/2021 - 28/02/2022 } 6.08 Shree Balaji Builders 26/02/2021
56 Narnaul PHED No. 2 Up gradation of existing 7.50 MLD capacity sewage treatment plant on Moving Bed Biological Reactor Technology (Attached growth process) to combined activated sludge process in conjunction with MBBR Bio film process with addition of new Mechanical Coarse and Fine Screens, Anoxic Tank, Internal Recirculation Pumps, at Narnaul Town Distt. Mahendergarh. { 01/06/2021 - 30/11/2022 } 5.84 Rathee Construction Company 26/05/2021
57 Narnaul PHED No. 2 Aug. of Drinking water supply scheme (canal based) for 122 Nos. villages @40 LPCD to 70LPCD in Narnaul Tehsil, District Mohindergarh. `Design, Construction and commissioning of 13.00 MLD SCADA based water treatment plant at WW Lehroda, 2 SandS tank, 1 no. Clear water tank, 1 No. Pump Chamber. { 18/09/2019 - 17/03/2021 } 13.44 Rathee Construction Company 18/09/2019
58 Narnaul PHED No. 3 Augmentation of Water supply scheme (Canal based) Water works at Bhalkhi for 61 Nos. villages, Tehsil Ateli Mandi, District Mohindergarh. “Construction of 3 Nos. Main Boosting Stations, 5 Nos. Intermediate Boosting Station and 38 No. Village Boosting Stations, Laying of 75672 Mtr. D.I. Rising Main lines of different sizes, 16790 Mtr. connecting pipelines of various boosting stations, and all other works contingent thereto”. { 24/09/2020 - 23/03/2021 } 19.44 Shree Balaji Builders 21/09/2020
59 Narnaul PHED No. 3 Augmentation of Water supply scheme (Canal based) Water works at Bhalkhi for 61 Nos. villages, Tehsil Ateli Mandi, District Mohindergarh. “Construction of Water works at Bhalkhi village comprising design, Construction and commissioning of 12.50 MLD SCADA based water treatment plant at Bhalkhi { 20/02/2019 - 19/08/2020 } 15.75 Anand Kumar Contt. 08/02/2019
60 Narwana PHED Narwana Town-Estimate to create Tertiary Treatment facility at 03 nos. Sewerage Treatment Plant of capacity 3.75 LD, 3.50 MLD and 2.00 MLD based on MBBR Technologies followed by chlorination in Narwana Town Distt. Jind. “ Up-gradation of existing sewerage treatment plant ( STP ) of 3.75 MLD, 3.50 MLD and 2.00 MLD capacity based on Moving Bed Bio Reactor (MBBR) technology located at Narwana Town, Jind City { 07/06/2021 - 06/12/2022 } 7.21 HITECH ENVIRO ENGINEERS AND CONSULTANTS PVT. LTD 26/05/2021
61 Nuh (P) PHED No. 1 Ranneywell-Aug. w/s sch. in quality aff. 80 no. vill. of F.P.Jhirka and Nagina Block and 1 No. town F.P.Jhirka from Yamuna Flood Plain by const. R/well and deep TW in Atba. `Laying, jointing, testing and comm. of 900mm r/main from MBS Atba to MBS Malhaka upto MBS Mahoon, Const. of 8 No. Steel bridge, Crossing of R/line with 3 mths trial run after comm. 5 year OandM including 1 year defect liability period andall other works contingent thereto` { 16/07/2018 - 15/01/2020 } 14.3 Chahar Construction Co. 06/07/2018
62 Nuh (P) PHED No. 1 Aug. drinking WS in Quality affect 80 vill. from Yamuna Flood Plain by const. Ranney well and deep TWs in Atba/ Sultapur `Const. of 1 Ranney well, MBS in vill. atba, Malhaka and Mahoon and Pump machy. Indep. feeder for Ranney well and MBS Atba, Malhaka, laying of 400mm i/d DI rising main from R/well to MBS Atba with 3 month trial period after commissioning, 5 Yrs mtc. including 1 Year defect liabiltiy period and other works contingent thereto` { 16/07/2018 - 15/01/2020 } 30.26 KNK Projects Pvt Ltd 06/07/2018
63 Nuh (P) PHED No. 1 F.P.Jhirka town- Aug. drinking w/s in quality affected 80 villages and 1 F.P.Jhirka town from Yamuna flood plain “Const. of 1 No. R/well, const. of MBS in village Atba, Malhaka and Mahoon and Pump Machy., I/d feeder for R/well and MBS Atba and MBS Malhaka, laying, jointing, testing and commissioning of 400mm i/d DI Rising main from R/well to MBS Atba”. (Part-B) For adjustment of proportionate cost of F.P.Jhirka Town. { 16/07/2018 - 15/01/2020 } 18 KNK Projects Pvt Ltd 06/07/2018
64 Nuh (P) PHED No. 1 Aug. w/s sch. in quality aff. 80 no. vill. of F.P.Jhirka and Nagina Block and 1 No. town F.P.Jhirka from Yamuna Flood Plain by const. R/well and deep TW in Atba. `Laying, jointing, testing and comm. of r/main from MBS Mahoon to 4 No. IBS, Const. of 4 No. IBS each in Sakras, Naryala Ferozepur, Kameda and Agon with 3 mths trial run after comm. 5 year OandM including 1 year defect liability period andall other works contingent thereto` { 21/09/2018 - 20/09/2019 } 9.8 Narender Singh Contractor 13/09/2018
65 Nuh (P) PHED No. 1 Aug. WS sch. in Quality aff. 80 Nos. vill. `Laying, Jointing and testing of Sub R/ main from MBS Malhaka to vill. Baded and Dondal, IBS Mahun, Sakras, Naryala, Kameda and Agon to SBS in various vill, IBS Mahun to F.P Jhirka Town, const. of 105 No. SBSs, from 25 KL to 175 KL, P/F of p. Machy. for SBS, laying of distr. PL in various vill. with 3 M trial run, 5 yr O and M after 1 year defect liability period and other works contingent thereto`. { 04/06/2019 - 03/06/2020 } 26.38 Narender Singh Contractor 27/05/2019
66 Nuh (P) PHED No. 1 Aug.W/S sch.in Q affected 80 Nos. vill. of F.P Jhirka and Nagina Block and 1 NO. Town F.P Jhirka `Laying of Sub R/main from MBS Malhaka to village Baded and Dondal, IBS Mahun, Sakras, Naryala, Kameda and Agon to SBS in various vill, IBS Mahun to F.P Jhirka Town, construction of 105 No. SBSs, from 25 KL to 175 KL, P/F P/machy for SBS, laying of distri. PL in various villages (Part-B) For adjustment of proportionate cost of F.P.Jhirka Town. { 04/06/2019 - 03/06/2020 } 26.38 Narender Singh Contractor 27/05/2019
67 Palwal PHED No. 1 Aug. W/S Scheme in Quality Affected 84 No. vills. `Prov. laying, jointing, testing and comm. of PCC pipe 800 mm i/d/ 700 mm i/d rising main from MBS Mohna and MBS Dudhola and laying, jointing, testing and comm. D.I. pipe line to connect IBS Mandkol and IBS Dudhola, const. of steel truss bridge, crossing of RW and NH with 3 mths trial run period, 5 year mtc. inc. 1 year defect liability period and all other works contingent thereto`. { 01/09/2017 - 31/08/2018 } 25.18 M/S Vichitra Prestressed Concrete Udyog Pvt. Ltd. 29/08/2017
68 Palwal PHED No. 1 Augmentation Drinking Water Supply Scheme in QualityAffected 84 No. villages of Prithla and Palwal constructionof Ranney Well and Deep Tubewell in village Mohna.`Construction of 4 Nos.Intermediate Boosting Station each in village Dudhola, Mandkol, Prithla andBhanakpur, laying of rising main from each intermediate boosting station tovillage SBS, construction of 39 No. SBS in various villages, crossing ofrailway line and National Highway etc. { 15/06/2020 - 14/06/2022 } 22.61 Sh. Hamid Hussain 29/05/2020
69 Palwal PHED No. 1 Aug. W/S Sch in Quality Aff 84 No. vills. Prov. laying, jointing, testing and comm. of PCC pipe 800 mm i/d/ 700 mm i/d rising main from MBS Mohna and MBS Dudhola and laying, jointing, testing and comm. D.I. pipe line to connect IBS Mandkol and IBS Dudhola, const. of steel truss bridge, crossing of RW and NH with 3 mths trial run period, 5yrs mtc. inc. 1yr defect liability period and all other works contingent thereto`.(At Risk and Cost) { 11/11/2018 - 10/11/2019 } 26.51 Concrete Udyog Jhansi M/S 02/11/2018
70 Palwal PHED No. 1 Aug.drinking Water Supply Scheme in quality affected 84 No villages of Prithla and Palwal block of Distt.Palwal and Ballabgarh block of Distt.Faridabad from Yamuna flood Plan by Cons. of Ranneywell and deep Tubewell in village Mohna. Const. of 3 Nos IBS each in village Dhatir, Kairaka and Ratipur. Laying of rising main from each IBS to village SBS, const. of 33 Nos SBS in various villages, providing independent feeder for IBS with 5 years operation and mtc including 1 year defected liability period after 3 months trail run period and all other works contingent thereto { 21/04/2018 - 20/04/2019 } 13.12 Nafe Singh Contractor Narwana 10/04/2018
71 Palwal PHED No. 1 Aug.drinking W/S Sch.in quality affected 84 No villages of Prithla, Palwal and Ballabgarh block of Distt.Palwal andFaridabad`-Const. of MBS in vill.Dudhola. Laying rising main from MBS Dudhola to 5 Nos IBS in various vill.Const.of 1 No.steel truss Bridge on Gaunchi drain with 3 months trial run period, 5 years OandM including 1 year defect liability period and all other works contingent thereto`. { 01/11/2017 - 30/04/2019 } 5.53 Sh. Jaibir Singh 27/10/2017
72 Palwal PHED No. 1 Aug. Drinking W/S sch. quality affected 84 Nos. villages of Palwal, Pirthla and Ballabgarh Block. `Const. of 2 no. ranneywell, installation of 2no. T/W, const. of MBS in village Mohna and pumping machinery, independent feeder for ranneywell and MBS including all crossing with 3 months trail run period, 5 yrs OandM incl. 1 year defect liability period for and all other works contigent thereto`. { 01/08/2017 - 31/01/2019 } 28.68 Advanced Infratech Pvt. Ltd 27/07/2017
73 Palwal PHED No. 1 Aug.drinking W/S Sch. in qlty affected 84No vills of Prithla and Palwal block of Distt.Palwal and Ballabgarh of Distt.FBD from Yamuna flood Plan.Const. of 4 Nos IBS each in village Duhdola,Prithla,Mandkol and Bhanakpur. Lay of rising main from each IBS to vill SBS, const of 39 Nos SBS in vari vills, prov. ind. feeder for IBS with 5yrs OandM incl. 1yr defected liability prd after 3 months trail run period and all other works contingent thereto { 07/07/2018 - 06/07/2019 } 18.79 Rajesh Kumar Contractor 27/06/2018
74 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at village Deeghot, District Palwal (Under Mahagram Yojna). { 13/11/2020 - 12/05/2022 } 8.51 Jasveer singh Contractor 28/10/2020
75 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities at village Aurangabad, District Palwal(Under Mahagram Yojna) Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible pumping set of 600/800 LPM and all other works contingent thereto. { 16/01/2021 - 15/07/2022 } 7.63 Jasveer singh Contractor 06/01/2021
76 Palwal PHED No. 3 Detailed Project Report for Providing Sewerage Facilities at village Sondhad, District Palwal(Under Mahagram Yojna).Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible 2 No. pumping set of 700/500 LPM, 15 mtr Head, providing, laying, jointing, cutting, testing of 200 mm i/d DI Rising Main from and all other works contingent thereto. { 28/12/2020 - 27/06/2022 } 6.45 Jasveer singh Contractor 17/12/2020
77 Palwal PHED No. 3 Providing CIPP (Technology of existing sewer line of size 600 mm i/d from Old Sohna Road Wine Shop to City Thana and 1000mm i/d RCC pipe sewer line from Mangla Medical Store to Parshu Ram Colony and desilting of sewer by Super Sucker Machine in various places of Palwal Town, Distt Palwal { 05/07/2021 - 04/01/2022 } 6.46 V N ENGINEERING COMPANY 30/06/2021
78 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at village Kambhi, District Palwal(Under Mahagram Yojna). { 13/11/2020 - 12/05/2022 } 6.53 Rajesh Kadian Siwah 28/10/2020
79 Palwal PHED No. 3 DPR for providing sewerage facility in village Bhiduki, Tehsil Hodel, Distt Palwal (Under Mahagram Yojna) Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible pumping set of 1000/1500 LPM, 15 mtr Head, providing, laying, jointing, cutting and testing of 200 mm to 500 mm i/d SWP sewer line and all other works contingent thereto. { 21/01/2021 - 20/07/2022 } 7.19 Rajesh Kadian Siwah 18/01/2021
80 Panipat PHED No. 2 PART-A- Sewerage System- Providing sewerage system in village Bapoli Distt. Panipat “Laying of 25.64 km sewerage network of different sizes in village Bapoli, Distt. Panipat. Operation and maintenance of Sewerage Scheme for 5 years after defect liability period of 1 year after trial run period of 3 months { 20/11/2020 - 19/05/2022 } 5.71 Rajesh Kadian Siwah 20/11/2020
81 Panipat PHED No. 2 Detailed Project Report For Shayama Prasad Mukherji Rurban Mission (Sewah Cluster) 9 Villages, District Panipat, “Providing, Installation of 6 tube wells upto 350m BGL, Construction of 6 tube well Chambers, boundry wall, laying of internal Distribution Pipe Lines, Supply, Erection, testing and commissioning of 6 submersible pumping sets for tube wells.... { 28/05/2020 - 27/11/2021 } 5.28 Nar singh Goel 21/05/2020
82 Panipat PHED No. 2 PART-B- Providing sewerage system in village Chulkana Distt. Panipat. Laying of 21.44 km sewerage network of different sizes in village Chulkana, Distt. Panipat. Operation and maintenance of Sewerage Scheme for 5 years { 24/12/2020 - 23/06/2022 } 6.67 Jasveer singh Contractor 24/12/2020
83 Panipat PHED No. 2 Part – A Water Supply Augmentation of water supply scheme by changing old pipe lines in village Sewah Distt. Panipat Part – B Sewerage System Providing sewerage system in village Sewah Distt. panipat { 11/09/2019 - 10/03/2021 } 8.62 H S Construction Company 11/09/2019
84 Rohtak PHED No. 2 Augmentation of Water Supply Scheme Nindana, “Design, testing , commissioning of automated PLC controlled SCADA based water purfication plant of 3 MLD capacity Part-B Sewerage system in Nindana ` construction of 2 no. intermediate pumping station consisting of 2 no. collecting tanks including screening chamber,inlet box, Operation and mtc. of 5 years for water supply including WTP`s and sewerage after defect liability period for 12 months { 09/09/2019 - 08/03/2021 } 9.5 Kulbir Singh 05/09/2019
85 Rohtak PHED No. 2 Nindana- construction of 2 no. intermediate pumping station consisting of 2 no. collecting tanks including screening chamber,inlet box, pump chambers over the collecting tank, supplying and installation of pumping machinery at the intermediate pumping station, supply , laying jointing and testing of stone ware pipes of size from 100 mm to 400 mm , construction of brick masonry manhole chamber, providing SFRC manhole covers and frames { 09/09/2019 - 08/03/2021 } 6.53 Kulbir Singh 05/09/2019
86 Sirsa PHED No. 1 Const. of 1 No. Collecting Tank, Const. of PC, 630 mm o/d HDPE pipe, installation of DG set, Pumping Machinery, etc. { 08/01/2020 - 07/08/2021 } 15.14 M/s Durga Const. Company 02/01/2020
87 Sirsa PHED No. 2 Designing, Const, Testing, Commissioning, O and M for 5 years after defect liability period of 12 months after 3 months successful trial run of Channel, 2 Nos. S/S Tanks, 25MLD Automated WTP , 1 No. CWT, SCADA system and all other electrical, mechanical, instrumentation and other works contingent there to complete in all respects on Turnkey basis at Village Panjuana, Sirsa Town, Haryana.” { 07/12/2017 - 06/03/2019 } 23.9 M/S Ashok Kumar Jain, Govt. Contractor 01/12/2017
88 Sirsa PHED No. 2 Laying of D.I. Rising Main from Canal to Main Water Works, Construction of One No. Pump Chamber of size 10`x12`-1 No., Generator Set 500 KVA-1 No. with Platform - 1 No., Transformer with Plateform - 1 No., Electric Meter Room-1 No., reconstruction / repairing of Boundary Wall, C.C. Road and Plinth Protection, Laying of 300mm dia D.I. Pipe Line at Mini-Sectt Water Works area and all other works contingent thereto { 10/12/2019 - 09/06/2021 } 8.5 Jai Parkash Garg 27/11/2019
89 Siwani PHED Augmentation of water supply scheme Loharu Town by Providing canal based water works, Distt. Bhiwani, { 21/09/2020 - 20/03/2022 } 21.46 Shree Balaji Builders 11/09/2020
90 Sohna PHED Prov. sewerage scheme and const. of Sewerage Treatement Plant for H.Mandi Town of Distt. Gurugram `Designing, const., erection, testing and commissioning of automatic and PLC controlled with SCADA 5.50 MLD main P/station, Rising main upto STP, const. of automatic and PLC controlled with SCADA 5.50 MLD Sewerage Treatment Plant based on Sequential Batch Reactor (SBR) Technology, including 700mm i/d RCC pipe effluent channel.(under State Plan.) { 09/12/2016 - 09/06/2018 } 7.5 SCC EICPL (JV M/s SHiv Const. Co. and M/s Enviro Infra Engineer Co.Ltd. 2120 U.E Jind) 05/12/2016
91 Sohna PHED Aug. Drinking W/S Scheme in Fluoride Affected 23 No. villages of Sohna Distt. Gurgram. `Supply and Erection of P/M at MBS Dudhola, laying of rising main from MBS Dudhola to IBS Ghangola, construction of IBS at Ghanghola, laying of sub rising main from IBS Ghanghola to village SBS, construction of 23 Nos. (Volume- I-II) { 27/07/2018 - 26/07/2019 } 5.65 Rajender Contractor, Punhana (Mewat) 13/07/2018
92 Sohna PHED Sohna Town and Rozeka Meo Aug. W/S scheme Design, const. andcommissioning of raw water pumping station at Budhera andrising main of PSC pipe line on turenkey basis comprasing ofinnelt channel, 2 no. S/S tank pump house, pumping machinery , including electrilcal, mechnical instrumentation works .Boundarywall, stff qtr,PSC pipe line, , surge control devices op. and maintaince for 3 years after defect liablity period of1 year { 01/02/2016 - 01/05/2016 } 27.39 Jain Const.Co.M/s 03/12/2009
93 Sohna PHED Design, Const.,erection , testing and commissioning , operation and Maintenance for 3 year after defect liability period of 12 months of canel based W/S Sch. for Sohna Town comprising of 2 Nos. storage and laying and testing of 600mm i/d, 450mm i/d , 300mm i/d DI Pipe Raising main upto Sohna Town and Rojka Meo , and all other works contingent thereto.(under NCRPB) { 01/02/2016 - 01/05/2016 } 18.81 Jain Cons. Company M/S 31/08/2009
94 Sohna PHED Design and Construction of Pumping Station, 1 No Collecting Tank, RCC Screening C/Pump Chamber, B.Wall, Providing and fixing Non Clog Sewage Submersible Pump Sets , Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 400 mm S.W. Pipe sewer, Construction of in balance approved colonies in Sohna Town Distt. Gurugram, Haryana.`` (UNDER NCRPB) { 16/07/2018 - 15/10/2019 } 10.47 Jain Construction Co. Hisar M/S 02/07/2018
95 Sonipat PHED No. 2 Aug.of sewerage Treatment plant work under NRCP at Sonipat `construction of New 25 MLD STP and repair of 30 MLD STP { 01/09/2013 - 31/05/2015 } 38 H.L. Handa 16/08/2013
96 Tohana PHED Providing, Laying, Jointing, Testing of SW pipe sewer and construction of manhole chambers at Jakhal Mandi Tehsil Tohana Distt. Fatehabad and all other works contingent thereto. { 15/07/2020 - 14/01/2022 } 6.85 OmParkash Contt. Berla 06/06/2020
97 Tohana PHED Providing sewerage scheme and Construction of Sewage Treatment Plant including Operation and Maintenance for 12 months during defect liability period after trail run of 3 months and Five years thereafter at Tohana Town of District Fatehabad ” { 15/10/2020 - 14/04/2022 } 5.79 M/s Shiv Construction Company Jind 25/09/2020
98 Yamuna Nagar PHED No. 1 DPR for designing of rising main from 20MLD STP MPS at Badhi Majra and 24MLD STP at Parwalon at Yamuna Nagar. `Design, construction, erection, testing and commissioning of rising main from 20 (10 plus 10) MLD STP at Badhri Majra nd 24MLD STP Parwalon, Yamuna Nagar, Pumping Station and Rising Main for safe disposal in River Yamuna near Udhri village, Yamuna Nagar and including operation and maintenance for 5 years. { 30/05/2019 - 28/05/2020 } 18.24 Jain Irrigation Systems Limited 27/05/2019
99 Yamuna Nagar PHED No. 1 Construction of Sewerage Treatment Plant and Sewerage Network in Saraswati Nagar (Mustafabad) Distt. Yamuna Nagar (Hon’ble C.M. Announcement). { 26/09/2017 - 25/09/2019 } 5.46 Inderjeet Singh Contractor 26/09/2017
100 Yamuna Nagar PHED No. 2 Design, Constm., erection, comm. of 10 MLD STP based on SBR Tech. at Badhi Majra Yamuna Nagar (Kapil Engg. Co. Rohtak) { 09/03/2018 - 08/09/2019 } 9.22 Kapil Engineering Company 01/03/2018
101 Yamuna Nagar PHED No. 2 Prov.Sew. facilities to 7 Nos. villages i.e. Aurangabad, Ishopur, Patashgarh, Mandebri, Panjeton Ka Majra, Heri Rangran, Sasoli in MC Y.Nagar (Under CM Announcement No. 10054), SW and RCC NP-3 Pipe Sewer of size 200mm, 250mm, 300mm, 400mm, 500mm, 600mm and 700mm in village Sasoli, Kheri Rangran, Panjeton Ka Majra and Mandebari, { 25/07/2017 - 24/07/2019 } 6.14 Sh. Anil Deswal 11/07/2017
×