"Awarded Works > 5 Crore"
Sr.No.Name of Procuring EntityBrief Description of Award (Start Date-End Date)Total Value (In Crores)Alloted To (Name of Agency)Date of Allotment
1 Ambala City PHED Moti Nagar Up gradation and commissioning after conversion of existing two units of 5 MLD each sewage treatment Plants based on Moving Bed Biological Reactor Technology (Attached growth process) to combined activated sludge process in conjunction with MBBR Bio film process with addition of Anoxic Tank, Internal Recirculation Pumps, Return activated sludge pumps, Aeration Tank, Treated Effluent Lifting Pumps with common Tertiary Treatment (10 MLD) { 16/02/2022 - 16/08/2023 } 8.39 M/s Sourabh Construction Company Pvt.Ltd. 15/02/2022
2 Ambala PHED Barara Cluster-Upgradation of W/S in one Cluster (Mullana) covering 14 Nos. villages, block Barara Distt Ambala under Shyama Parshad Mukherji Rurban Mission (SPMRM) `Instt. of T/Ws, Supplying and erection of Sub P sets, Const. of civil comp laying of dist system connection rising mains, Const. and Commissioning of Boosting Stns with erection of horizontal split casing clear water pumps, Provd Gen sets and all other works { 15/03/2022 - 14/09/2023 } 19.93 ANURAG GOEL 08/03/2022
3 Bawal PHED Master sewerage Scheme Dharuhera Town Distt. Rewari (ON RISK AND COST OF SH. RAJENDER CONTRACTOR R/O HOUSE NO. 5845, SHIVAJI NAGAR, TEH. and DISTT. GURUGRAM) { 01/04/2020 - 30/06/2020 } 5.14 Vinod Manocha, Contractor (3) 16/04/2018
4 Bhiwani PHED No. 1 Up gradation of existing sewege treatment plant of 20 MLD capacity ( 2 Nos x10 MLD each ) based on moving bed reactor (MBBR) technology to tertiary treatment plant located at Dhana Road in Bhiwani Town { 17/03/2021 - 16/09/2022 } 15 Rathee Construction Company 15/03/2021
5 Charkhi Dadri PHED Providing and laying HDPE rising main for treated effluent from existing 2 No. STP.s upto drain No. 8 Charkhi Dadri Const. of 1 No. Pump chamber, 1 No. collecting tank at jhajjar road STPs laying of 37700 mtr. { 15/09/2020 - 14/06/2021 } 31.74 Jain Irrigation Systems Limited 02/09/2020
6 Charkhi Dadri PHED Providing canal ased water supply scheme for sirsali Group of 12 No. Village constructing canal based water works at village { 05/04/2020 - 04/10/2021 } 12.71 M/S MAHALAXMI CONSTRUCTION COMPANY 27/03/2020
7 Charkhi Dadri PHED Proc canal based water supply scheme avillage ninar badesara gr of 35 no. Villages , ` const of raw water pumping station at with intermediate bs at incl o and m of 5 years and all other works contingent thereto { 28/03/2021 - 27/09/2022 } 33.82 M/S MAHALAXMI CONSTRUCTION COMPANY 24/03/2021
8 Charkhi Dadri PHED Mehra:- Providing canal based water supply scheme form Mehra Group of 6 No. village constructing canal based water work a village mehra. { 25/03/2020 - 24/08/2021 } 7.92 Suresh Kumar, Contractor 13/03/2020
9 Faridabad PHED No. 1 Detailed Project Report for Augmentation Water Supply Scheme at Village Tigaon (95) @155 LPCD Block Faridabad Constituency Tigaon Distt. Faridabad (Under Rural Augmentation) Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at Village Tigaon, Block Faridabad Tehsil and District Faridabad (Under Mahagram Yojna) Under CM Announcement. { 04/06/2019 - 03/12/2020 } 14.33 Mehta Construction co. M/s 04/06/2019
10 Fatehabad PHED Augmentation of Water Supply Scheme and Construction of 2nd Water Works Village Gorakhpur Tehsil and . Design, Construction, Testing and commissioning of 1.00 MLD Water Treatment Plant at Old Water Works and 1 MLD Water Treatment Plant 2nd Water works Construction of Raw Water Pumping Station Near Fatehabad Branch at Jandli Kalan Road Gorakhpur { 21/08/2019 - 20/02/2021 } 6.09 Jai Shree Balaji Const Co. Panipat. 14/08/2019
11 Fatehabad PHED Up-gradation and commissioning after conversion of existing 10 MLD capacity sewage treatment based on moving Bed BRT to combined activated sludge process in conjunction with MBBR Bio film process with, Anoxic Tank, Internal Recirculation Pumps, Treated effluent lifting pumps with tertiary treatment based on Deep Bed Filters followed by chlorination in existing STP complete in al respect { 09/10/2018 - 08/01/2020 } 5.59 Shree Balaji Builders 03/10/2018
12 Fatehabad PHED Aug. of canal based ww Bhuna Town “Const of inlet channel, ss tank, wtp fully automated with PLC/ SCADA system, rwp ump house, cwt, DGH sets and transformers at WW, raising and repair of boundary wall, supply erection, comm of pm, elect, mech piping instrumentation work and laying, jointing, cutting of DI rising main pipe line for Zone No. 1, 2, 3, 4, 5 and 6 of Bhuna town including OandM for 5 years after completion of 3 months trial run { 19/12/2017 - 18/03/2019 } 8.56 Maha laxmi Const. Company M/S 13/12/2017
13 Gohana PHED No. 1 TENDER NO. 2020_HRY_151667_1-BHAINSWAL KALAN-PROVIDING SEWERAGE SYSTEM (SEWAGE TREATMENT PLANT (STP)) IN VILLAGE BHAINSWAL KALAN DISTT. SONIPAT (NAME OF WORK AS PER DNIT ATTACHED) { 15/01/2021 - 14/07/2022 } 5.75 M/s. SFA and Associates 06/01/2021
14 Gohana PHED No. 1 Tender No. 2019_HRY_80989_1-PART –A WATER SUPPLY AUGMENTATION WATER SUPPLY SYSTEM OF VILLAGE KHANPUR KALAN DISTT. SONIPAT { 23/08/2019 - 22/02/2021 } 7.09 Rohtash Kumar Contractor 13/08/2019
15 Gohana PHED No. 1 Tender No. 2019_HRY_80989_1- PART B SEWERAGE SYSTEM - PROVIDING SEWERAGE SYSTEM IN VILLAGE KHANPUR KALAN { 23/08/2019 - 22/02/2021 } 8.14 Rohtash Kumar Contractor 13/08/2019
16 Gohana PHED No. 1 Tender No. 2022_HRY_206110_1-Up gradation and commissioning after conversion of existing 8.3 MLD capacity sewage treatment Plant based on Moving Bed Biological Reactor Technology (Name of Work as Per DNIT) { 01/04/2022 - 31/03/2023 } 8.64 RAJEEV KUMAR GOEL CONTRACTORS 22/03/2022
17 Gohana PHED No. 1 Tender No. 2020_138952_1- (A) Water Supply - Providing Water Supply in Village Bhainswal Kalan Mithan and Bhainswal Kalan Bawla. (Name as per DNIT) { 01/09/2020 - 31/03/2022 } 7 Jai Shree Balaji Const Co. Panipat. 20/08/2020
18 Gohana PHED No. 1 Tender No. 2020_138952_1- (B) Providing Sewerage System in Village Bhainswal Kalan Mithan and Bhainswal Kalan Bawla (Name as per DNIT) { 01/09/2020 - 31/03/2022 } 10.05 Jai Shree Balaji Const Co. Panipat. 20/08/2020
19 Gohana PHED No. 1 Tender No. 2021_HRY_155623_1 - SHAMRI GROUP: DPR FOR PROVIDING RAW WATER TO EXISTING 3 W/W ie SHAMRI, CHIRANA and MUNDLANA FROM JLN CANAL, UPDATING OF EXISTING STRUCTURES OF W/W. CONSTRUCTION OF C/B WATER WORKS AT KAILANA KHAS FOR GROUP OF 3 VILLAGES, PROVIDING FHTC and LAYING OF BALANCE PIPE LINES IN VILLAGES DISTT. SONIPAT. (NAME OF WORK AS PER DNIT) { 01/04/2021 - 31/03/2022 } 7.6 Nafe Singh Contractor 22/03/2021
20 Gurugram PHED Construction of Inlet Channel, Hodies, RCC Sump well, Pump Chamber, Laying, Jointing and Testing of Raw Water rising main from 250 mm to 600 mm i/d D.I. K9 pipe from WW Iqbalpur to W/W Mushedpur, Birhera and Mehchana and Providing canal based water supply in adational 8 Nos. villages and also providing FHTC { 01/08/2021 - 31/01/2023 } 25.71 Narender Singh Contractor 23/06/2021
21 Gurugram PHED Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 350mm, 400 mm, 450mm S.W. Pipe and 500 mm, 600 mm, 700 mm and 900 mm i/d RCC Np3 pipe sewer, construction of brick masonry manholes chambers and reconstruction of streets with interlocking tiles complete in all respect and and all other works contingent there to in village manesar { 15/07/2018 - 15/07/2019 } 17.04 Jain Construction Co. Hisar M/S 21/06/2018
22 Gurugram PHED Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 350mm, 400 mm, 450mm S.W. Pipe and 500 mm, 600 mm, 900 mm and 1200 mm i/d RCC Np3 pipe sewer, construction of brick masonary manholes chambers and reconstruction of streets with interloacking tiles complete in all respect and and all other works contingent there to in village Naharpur Kasan { 15/07/2018 - 15/07/2019 } 7.09 Jain Construction Co. Hisar M/S 21/06/2018
23 Gurugram PHED DNIT for `Designing, Constructing, Testing, Commissioning of Boundary Wall with iron gate 400 mtr, laying of 500 mm i/d D.I.- K9 Rising main, 100 mm to 450 mm i/d D.I. K7 internal distribution, including providing and fixing D.I.Spls. and reconstruction of streets with interloackingtiles complete in all respect and and all other works contingent there to and Operation and Maintenance for 5 year in village NaharpurKasan Haryana.`` { 15/07/2018 - 15/07/2019 } 7.09 Jain Construction Co. Hisar M/S 21/06/2018
24 Gurugram PHED DNIT for `Designing, Constructing, of Boundary Wall with iron gate 220 mtr, laying andTesting, Commissioning of 700 mm and 500 mm i/d D.I.-K9 Rising main, 100 mm to 450 mm i/d D.I. K7 internal distribution, including providing and fixing D.I.Spls. and reconstruction of streets with interlockingtiles complete in all respect and and all other works contingent there to and Operation and Maintenance at village Manesar { 15/07/2018 - 15/07/2019 } 17.04 Jain Construction Co. Hisar M/S 21/06/2018
25 Hansi PHED Part -A : Kapro :- Upgradation of WS Scheme and Const. of 2nd WW Kapro Distt. Hisar ` Const. of 2 No. RCC FB, 2 Nos RCC CWT at 1st w/w, 400mm i/d RCC NP2 pipe IC, 2 No. B/L S/S Tank, 2 Nos. RCC S/S Well, 2.00MLD WTP, 2 No. RCC CWT, 1 No. PC, B/Wall etc. { 20/09/2019 - 19/03/2021 } 5.59 Bharat bhushan Contractor 19/09/2019
26 Hansi PHED Part – B : Kapro :- Providing sewerage facilities and sewerage treatment plant in village Kapro Distt. Hisar, “ Laying of Sewer line, construction of manhole and House sewer connection intercepting chamber for sewerage system in village Kapro Distt. Hisar and all other work contingent thereto { 20/09/2019 - 19/03/2021 } 8.65 Bharat bhushan Contractor 19/09/2019
27 Hansi PHED Hansi Town – Providing and laying of sewer line in balance streets of various colony Hansi Town CM Announcement `Laying of sewer line, construction of main hole, repair and raising of manhole and construction of IPS etc. and all other works contingent thereto { 24/04/2020 - 23/10/2021 } 6.34 M/S Sat Narain Gupta 20/04/2020
28 Hansi PHED Providing sewerage facilities and sewerage treatment plant in village Petwar, Distt. Hisar Under Mahagram Yojna, “Laying of sewerage , construction of manhole and House sewer connection intercepting chamber for sewerage system in village Petwarand all other works contingent thereto { 08/11/2019 - 07/05/2021 } 6.39 Ravinder Sharma 06/11/2019
29 Hisar PHED No. 2 MAYYAR: Aug/Reno of W/S scheme including FHTC at village Mayyar Distt. Hisar (Under JJM Cat-II) `Const of 2 No RCC SS Tank, 2 Nos. RCC CWT, RCC SS well, PC, SV Houdi, Earth Filling, Raising of B/Wall, Dismentling of 6 Nos. FB, Const of 1 No. Rapid Sand Filter 1.00 MLD, Pumping Machinery, Disty System, FHTC and U/G CWT, B/wall, PC DI specials, 6` DI R/main, OandM of WTP of 1.00 MLD for 5 yrs after 12 mnths defect liability period after 3 mnths { 31/03/2022 - 30/03/2023 } 5.41 Suresh Kumar, Contractor 24/03/2022
30 Hisar PHED No. 2 Barwala Town Estimate for Providing and laying HDPE Rising main for Treated Effluent from Existing STP to Proposed Pond Distt Hisar. Constt. of RCC Collecting tank, BM PC C.C. Road, Excavation of Pond, Const. of Brick Masonry BW, Laying of HDPE PN-4 PE-80 Rising Main from STP to Pond, Providing and Installation of Pumping Machinery with all accessories and all other works contingent thereto`. { 15/02/2021 - 15/02/2022 } 5.18 M/s. SFA and Associates 10/02/2021
31 Jhajjar PHED No. 3 Shyama Parsad Mukherji Rurban Mission (Badli Cluster) 17 Nos. villages, District Jhajjar, up-gradation of water supply schemes from 70 to 135 LPCD for 12 villages falls under PHED No. 3, Jhajjar, District Jhajjar { 01/10/2019 - 31/03/2021 } 6.75 Chahar Construction Co. 11/09/2019
32 Jind PHED No. 1 Providing and laying of sewerline in newly approved colonies and construction of STP for Jind town { 24/11/2017 - 23/05/2019 } 11.12 The Dikadla Co.op.L/C Society Ltd.,Dikadla Tehsil Samalkha Distt. Panipat. 16/11/2017
33 Jind PHED No. 1 Up gradation and commissioning after conversion of existing 15 MLD capacity sewage treatment based on Moving Bed Biological Reactor Technology (Attached growth process) to combined activated sludge process in conjunction with MBBR Bio film process with addition of Anoxic Tank, Internal Recirculation Pumps, Treated Effluent Lifting Pumps with Tertiary Treatment. { 16/05/2018 - 15/08/2019 } 8.39 M/s Shiv Construction Company Jind 11/05/2018
34 Jind PHED No. 1 Providing and laying of 560 mm o/d HDPE Rising Main for sewerage from 5 MLD Existing STP (Ahirka) to Kalwa-Kinana Drain for Jind town Distt. Jind,`Design, Construction, Erection, Testing and Commissioning of 560 mm o/d HDPE rising main from 5 MLD Existing MLD to Kalwa-Kinana Drain etc. { 01/10/2019 - 30/09/2020 } 16 Jain Irrigation Systems Limited 18/09/2019
35 Jind PHED No. 2 Muana:- Aug. Water Supply Scheme for village Muana under Mahagarm Yojna { 16/09/2019 - 15/03/2021 } 8.26 M/s COMPETENT BUILDERS AND CONTRACTORS 12/09/2019
36 Jind PHED No. 2 Muana:Prov. Sewerage System in Village Muana Distt. Jind { 16/09/2019 - 15/03/2021 } 10.71 M/s COMPETENT BUILDERS AND CONTRACTORS 12/09/2019
37 Kaithal PHED No. 1 Pai-Providing Sewerage System in village Pai Design, Const. erection testing and commissioning of MPS of 3.50 MLD with peak factor 2.5 and STP of 3.50 MLD based on SBR laying of 400 mm i/d HDPE pipe of length 1600 mtr for disposal of Treated Effluent from STP to drain including Room, CCTV cameras, Transformer, DG set independent feeder at STP including OandM of 12 months run of 3 months and 10 years { 21/06/2019 - 20/06/2020 } 5.85 U.B.A. Constructions 13/06/2019
38 Kaithal PHED No. 1 E-Tender No. 106911- Pai(Adarsh village) Revised estimate for Up-gradation of water supply Pai Tehsil Pundri District Kaithal “Design , testing commissioning of authomated PLC controlled SCADA based water purification plant of 1.00 MGD (4.54 MLD) capacity at 2nd water works Pai construction of 1 No. S/S Tank and 2 No. RCC Clear Water Tank working depth and supplying and installation of 2 Nos Horizontal split { 08/03/2019 - 07/03/2020 } 6.39 Rohtash Kumar Contractor 26/02/2019
39 Kaithal PHED No. 2 Construction of Sewerage Treatment Plant and Sewerage Network in village Siwan Tehsil Guhla Distt. Kaithal,” Supplying, Laying, Jointing and testing of stone ware pipes of 200mm to 400mm and 500mm to 600mm of RCC NP3 pipes and construction of Brick masonry Manhole chambers and SFRC Manhole covers and frames and all other works contingent thereto { 16/08/2017 - 15/05/2018 } 10.54 Rohtash Kumar Contractor 09/08/2017
40 Kaithal PHED No. 2 Siwan Detail Project Report for construction of Sewage Treatment Plant and Sewerage Network in village Siwan Tehsil Guhla and Distt Kaithal (Haryana) “Design, Construction, erection, testing and Commissioning of main pumping station of 4.50 MLD with peak factor 2.50 consisting of collecting tank with screening with chamber size, village Siwan Tehsil Guhla and District Kaithal Haryana. { 10/09/2019 - 09/09/2020 } 12.8 V.S.Enterprises 06/09/2019
41 Karnal PHED No. 1 Nighdu:-Aug. of Sewerage Scheme for Village Nighdu,Karnal under Swaran Jayanti Mahagram Yojna. “Prov laying cutting jointing of 200 mm, 250 mm, 300 mm and 400 mm SW pipe RCC NP3 Pipe sewer const. of Manhole chamber, incerptng chamber prov house sewer conn. as per standard drawing operation, mtc. for 12 mnths during defect liability period after trial and 5 year { 16/08/2019 - 15/08/2020 } 8.72 ANURAG GOEL 13/08/2019
42 Karnal PHED No. 2 Up-gradation of water supply and providing sewerage system in village Kohand Block Gharaunda Distt. Karnal “Providing, Laying, Jointing, cutting and testing of Sewerage Network System of S.W. pipe size 200 mm dia, 250 mm dia, 300 mm dia, 400 mm dia and 500 mm dia, construction of manhole, Construction of interceptic chamber, making of household connections. Operation and maintenance of water supply scheme and Sewerage Network System { 18/09/2020 - 17/03/2022 } 6.1 M/s M.R Construction Company Kaithal 08/09/2020
43 Kosli PHED Detailed Project for upgradation of W/S system from 70 LPCD to 135 LPCD for 08 Nos. covered under SPMRM, ` Const. of 02 Nos. Inde. canal based W/W for village Bhakli and Chawwa including all required electrical and mechanical equipments. { 10/06/2020 - 09/12/2021 } 6.49 Rakesh Yadav 02/06/2020
44 Kurukshetra PHED Tender no.104789_1 Providing Sewerage network and construction of sewage treatment plant in ismailabad town { 28/11/2019 - 27/05/2021 } 9.55 Inderjeet Singh Contractor 13/11/2019
45 Mandi Dabwali PHED MANDI DABWALI - Updating, Renovation of Water Works, Construction of 2 nos. Boosting Stations and Providing and Laying of Water Supply Distribution System at Mandi Dabwali Distt. Sirsa. `Providing and Laying of 900mm i/d RCC Pipe Channel 490 mtrs., Construction of 2 No. S/S Tanks, Raw water and Clear water Suction Well, Re-Construction of Boundary wall at water Works, Boundary wall at B/Stn. Chouhan Nagar, etc. { 25/05/2022 - 24/11/2023 } 6.42 M/S Sat Narain Gupta 17/05/2022
46 Mandi Dabwali PHED Providing and Laying of Sewerage System in Recently Approved Colonies at Mandi Dabwali Distt. Sirsa. Providing and laying of Sewer Lines i.e. 200mm, 250mm, 300mm dia S.W. pipe in recently approved colonies and 280mm o d Rising Main HDPE Pipe PE80 grade and PN4 from Proposed IPS to existing 16.50 MLD STP at Mandi Dabwali Town Distt. Sirsa { 21/09/2020 - 20/09/2021 } 5.19 MANGAT RAI 14/09/2020
47 Mandi Dabwali PHED Augmentation water supply scheme to Village Ganga Distt. Sirsa. Providing and laying of 700mm dia RCC Pipe Class NP-2 and construction of SS Tank 1 No., S/S Tank 1 No., RW Water Suction and CW Scour Tank, RCC High Level Tank 1 No., Filtration Plant - 2 MLD SCADA based - 1 No., RCC Clear Water Tank 3 No., Pump Chamber with RCC Column , Boundary Wall, Toilet Block 1 No., etc. and all other works contingent thereto { 19/08/2019 - 18/02/2021 } 5.65 M/s Balaji Construction Company 14/08/2019
48 Mandi Dabwali PHED Providing Sewerage System and construction of STP at Village Ganga Distt. Sirsa. Providing and laying of various sizes of Sewerage Lines and construction of manholes, 1 No. Collecting tank and screening chamber, inspection chamber, pump chamber, Boundary Wall with Iron Gate, Rising Main, Toilet Block, Staff Quarter, Instt. of pumping machinery and all required Electrical, Mechanical Equipment’s etc. at village Ganga. { 19/08/2019 - 18/02/2021 } 9.99 M/s Balaji Construction Company 14/08/2019
49 Mohindergarh PHED Satnali Village Aug. of Drinking W/s Scheme 25 Nos villages“Construction of 1 Raw water Pumping station, 1 water work, 4 IBS, 32 VBS at different villages comprising Design, Construction, Testing and Commissioning of 8.50 MLD SCADA based water Treatment plant, Balancing capacity reservoir, S and S Tanks, Clear waterTanks, Pump chambers, Boundary wall, R/W and C/W Rising main lines, Internal Distribution of 25 villages and 9 Dhanies. { 14/02/2019 - 13/02/2020 } 34.34 ANAND ENGINEERS 06/02/2019
50 Mohindergarh PHED Part-1 W/s- Aug. of drinkig w/s scheme for 25 Nos villages on Canal based . Part-2 Sewerage System Prov. sewerage system in village Satnali Distt. Mohindergarh (Under Swaran Jayanti Mahagram Yajna)`Laying of Sewerage network of various size of construction of Manholes in village Satnali OandM of 5 Years including defect liability period after trial run period of 3 Months and all other works contingent there to. { 17/01/2019 - 16/01/2020 } 7.61 Vikash Badesra Contt. 09/01/2019
51 Narnaul PHED No. 1 Design, construction, erection and commissioning of STP of Capacity 3.00 MLD on SBR technology, MPS of Capacity 9.00 MLD, laying of 600 mm i/d RCC NP-3 pipe treated effluent channel, construction of 1 No. Staff Quarter, boundary wall, CC Path, land scaping, MCC Panel Room, 5 Nos. CCTV Cameras, Electric Transformer, D.G. Set and all other contingent electrical, mechanical piping { 01/03/2021 - 28/02/2022 } 6.08 Shree Balaji Builders 26/02/2021
52 Narnaul PHED No. 2 Aug. of Drinking water supply scheme (canal based) for 122 Nos. villages @40 LPCD to 70LPCD in Narnaul Tehsil, District Mohindergarh. `Design, Construction and commissioning of 13.00 MLD SCADA based water treatment plant at WW Lehroda, 2 SandS tank, 1 no. Clear water tank, 1 No. Pump Chamber. { 18/09/2019 - 17/03/2021 } 13.44 Rathee Construction Company 18/09/2019
53 Narnaul PHED No. 2 Up gradation of existing 7.50 MLD capacity sewage treatment plant on Moving Bed Biological Reactor Technology (Attached growth process) to combined activated sludge process in conjunction with MBBR Bio film process with addition of new Mechanical Coarse and Fine Screens, Anoxic Tank, Internal Recirculation Pumps, at Narnaul Town Distt. Mahendergarh. { 01/06/2021 - 30/11/2022 } 5.84 Rathee Construction Company 26/05/2021
54 Narnaul PHED No. 3 Augmentation of Water supply scheme (Canal based) Water works at Bhalkhi for 61 Nos. villages, Tehsil Ateli Mandi, District Mohindergarh. “Construction of Water works at Bhalkhi village comprising design, Construction and commissioning of 12.50 MLD SCADA based water treatment plant at Bhalkhi { 20/02/2019 - 19/08/2020 } 15.75 Anand Kumar Contt. 08/02/2019
55 Narnaul PHED No. 3 Augmentation of Water supply scheme (Canal based) Water works at Bhalkhi for 61 Nos. villages, Tehsil Ateli Mandi, District Mohindergarh. “Construction of 3 Nos. Main Boosting Stations, 5 Nos. Intermediate Boosting Station and 38 No. Village Boosting Stations, Laying of 75672 Mtr. D.I. Rising Main lines of different sizes, 16790 Mtr. connecting pipelines of various boosting stations, and all other works contingent thereto”. { 24/09/2020 - 23/03/2021 } 19.44 Shree Balaji Builders 21/09/2020
56 Narnaul PHED No. 3 DPR FOR AUGUMENTATION CANAL BASED WATER SUPPLY SCHEME FOR VILLAGE GAHRA GROUP OF 29 NOS VILLAGES and 2 NOS. DHANIES DISTT. MOHINDERGARH. E/C – 9976.66 Lakh “Construction of Raw water Pumping Station Near M.G. Canal and Independent water works Village Gahra Distt. Mohinder Garh. { 19/01/2022 - 18/01/2023 } 21.4 Rakesh Yadav 17/01/2022
57 Narwana PHED Narwana Town-Estimate to create Tertiary Treatment facility at 03 nos. Sewerage Treatment Plant of capacity 3.75 LD, 3.50 MLD and 2.00 MLD based on MBBR Technologies followed by chlorination in Narwana Town Distt. Jind. “ Up-gradation of existing sewerage treatment plant ( STP ) of 3.75 MLD, 3.50 MLD and 2.00 MLD capacity based on Moving Bed Bio Reactor (MBBR) technology located at Narwana Town, Jind City { 07/06/2021 - 06/12/2022 } 7.21 HITECH ENVIRO ENGINEERS AND CONSULTANTS PVT. LTD 26/05/2021
58 Nuh (P) PHED No. 1 Aug. w/s in Quality aff. 80 vill. of F.P.Jhirka and Block Nagina and 1 town from Yamuna flood plain by const. Ranney well and TWs in village Atba `Laying, testing commissioning of 900mm i/d DI rising main from MBS Atba to MBS Malhaka upto MBS Mahoon, Const. of 8 No. steel truss bridge , crossing of Railway line, and NH with 3 months trial run after commissioning 5 yr mtc.. i/c 1 yr. defect liability period. { 16/07/2018 - 15/01/2020 } 14.3 Chahar Construction Co. 06/07/2018
59 Nuh (P) PHED No. 1 Aug. w/s sch. in quality aff. 80 no. vill. of F.P.Jhirka and Nagina Block and 1 No. town F.P.Jhirka from Yamuna Flood Plain by const. R/well and deep TW in Atba. `Laying, jointing, testing and comm. of r/main from MBS Mahoon to 4 No. IBS, Const. of 4 No. IBS each in Sakras, Naryala Ferozepur, Kameda and Agon with 3 mths trial run after comm. 5 year OandM including 1 year defect liability period andall other works contingent thereto` { 21/09/2018 - 20/09/2019 } 9.8 Narender Singh Contractor 13/09/2018
60 Nuh (P) PHED No. 1 Aug. WS sch. in Quality aff. 80 Nos. vill. `Laying, Jointing and testing of Sub R/ main from MBS Malhaka to vill. Baded and Dondal, IBS Mahun, Sakras, Naryala, Kameda and Agon to SBS in various vill, IBS Mahun to F.P Jhirka Town, const. of 105 No. SBSs, from 25 KL to 175 KL, P/F of p. Machy. for SBS, laying of distr. PL in various vill. with 3 M trial run, 5 yr O and M after 1 year defect liability period and other works contingent thereto`. { 04/06/2019 - 03/06/2020 } 26.38 Narender Singh Contractor 27/05/2019
61 Nuh (P) PHED No. 1 Aug.W/S sch.in Q affected 80 Nos. vill. of F.P Jhirka and Nagina Block and 1 NO. Town F.P Jhirka `Laying of Sub R/main from MBS Malhaka to village Baded and Dondal, IBS Mahun, Sakras, Naryala, Kameda and Agon to SBS in various vill, IBS Mahun to F.P Jhirka Town, construction of 105 No. SBSs, from 25 KL to 175 KL, P/F P/machy for SBS, laying of distri. PL in various villages (Part-B) For adjustment of proportionate cost of F.P.Jhirka Town. { 04/06/2019 - 03/06/2020 } 26.38 Narender Singh Contractor 27/05/2019
62 Nuh (P) PHED No. 1 Ranneywell-Aug. w/s sch. in quality aff. 80 no. vill. of F.P.Jhirka and Nagina Block and 1 No. town F.P.Jhirka from Yamuna Flood Plain by const. R/well and deep TW in Atba. `Laying, jointing, testing and comm. of 900mm r/main from MBS Atba to MBS Malhaka upto MBS Mahoon, Const. of 8 No. Steel bridge, Crossing of R/line with 3 mths trial run after comm. 5 year OandM including 1 year defect liability period andall other works contingent thereto` { 16/07/2018 - 15/01/2020 } 14.3 Chahar Construction Co. 06/07/2018
63 Nuh (P) PHED No. 1 Aug. drinking WS in Quality affect 80 vill. from Yamuna Flood Plain by const. Ranney well and deep TWs in Atba/ Sultapur `Const. of 1 Ranney well, MBS in vill. atba, Malhaka and Mahoon and Pump machy. Indep. feeder for Ranney well and MBS Atba, Malhaka, laying of 400mm i/d DI rising main from R/well to MBS Atba with 3 month trial period after commissioning, 5 Yrs mtc. including 1 Year defect liabiltiy period and other works contingent thereto` { 16/07/2018 - 15/01/2020 } 30.26 KNK Projects Pvt Ltd 06/07/2018
64 Nuh (P) PHED No. 1 F.P.Jhirka town- Aug. drinking w/s in quality affected 80 villages and 1 F.P.Jhirka town from Yamuna flood plain “Const. of 1 No. R/well, const. of MBS in village Atba, Malhaka and Mahoon and Pump Machy., I/d feeder for R/well and MBS Atba and MBS Malhaka, laying, jointing, testing and commissioning of 400mm i/d DI Rising main from R/well to MBS Atba”. (Part-B) For adjustment of proportionate cost of F.P.Jhirka Town. { 16/07/2018 - 15/01/2020 } 18 KNK Projects Pvt Ltd 06/07/2018
65 Palwal PHED No. 1 Aug. Drinking W/S sch. quality affected 84 Nos. villages of Palwal, Pirthla and Ballabgarh Block. `Const. of 2 no. ranneywell, installation of 2no. T/W, const. of MBS in village Mohna and pumping machinery, independent feeder for ranneywell and MBS including all crossing with 3 months trail run period, 5 yrs OandM incl. 1 year defect liability period for and all other works contigent thereto`. { 01/08/2017 - 31/01/2019 } 28.68 Advanced Infratech Pvt. Ltd 27/07/2017
66 Palwal PHED No. 1 Aug. W/S Scheme in Quality Affected 84 No. vills. `Prov. laying, jointing, testing and comm. of PCC pipe 800 mm i/d/ 700 mm i/d rising main from MBS Mohna and MBS Dudhola and laying, jointing, testing and comm. D.I. pipe line to connect IBS Mandkol and IBS Dudhola, const. of steel truss bridge, crossing of RW and NH with 3 mths trial run period, 5 year mtc. inc. 1 year defect liability period and all other works contingent thereto`. { 01/09/2017 - 31/08/2018 } 25.18 M/S Vichitra Prestressed Concrete Udyog Pvt. Ltd. 29/08/2017
67 Palwal PHED No. 1 Aug. W/S Sch in Quality Aff 84 No. vills. Prov. laying, jointing, testing and comm. of PCC pipe 800 mm i/d/ 700 mm i/d rising main from MBS Mohna and MBS Dudhola and laying, jointing, testing and comm. D.I. pipe line to connect IBS Mandkol and IBS Dudhola, const. of steel truss bridge, crossing of RW and NH with 3 mths trial run period, 5yrs mtc. inc. 1yr defect liability period and all other works contingent thereto`.(At Risk and Cost) { 11/11/2018 - 10/11/2019 } 26.51 Concrete Udyog Jhansi M/S 02/11/2018
68 Palwal PHED No. 1 Augmentation Drinking Water Supply Scheme in QualityAffected 84 No. villages of Prithla and Palwal constructionof Ranney Well and Deep Tubewell in village Mohna.`Construction of 4 Nos.Intermediate Boosting Station each in village Dudhola, Mandkol, Prithla andBhanakpur, laying of rising main from each intermediate boosting station tovillage SBS, construction of 39 No. SBS in various villages, crossing ofrailway line and National Highway etc. { 15/06/2020 - 14/06/2022 } 22.61 Sh. Hamid Hussain 29/05/2020
69 Palwal PHED No. 1 Aug.drinking Water Supply Scheme in quality affected 84 No villages of Prithla and Palwal block of Distt.Palwal and Ballabgarh block of Distt.Faridabad from Yamuna flood Plan by Cons. of Ranneywell and deep Tubewell in village Mohna. Const. of 3 Nos IBS each in village Dhatir, Kairaka and Ratipur. Laying of rising main from each IBS to village SBS, const. of 33 Nos SBS in various villages, providing independent feeder for IBS with 5 years operation and mtc including 1 year defected liability period after 3 months trail run period and all other works contingent thereto { 21/04/2018 - 20/04/2019 } 13.12 Nafe Singh Contractor Narwana 10/04/2018
70 Palwal PHED No. 1 Aug.drinking W/S Sch.in quality affected 84 No villages of Prithla, Palwal and Ballabgarh block of Distt.Palwal andFaridabad`-Const. of MBS in vill.Dudhola. Laying rising main from MBS Dudhola to 5 Nos IBS in various vill.Const.of 1 No.steel truss Bridge on Gaunchi drain with 3 months trial run period, 5 years OandM including 1 year defect liability period and all other works contingent thereto`. { 01/11/2017 - 30/04/2019 } 5.53 Sh. Jaibir Singh 27/10/2017
71 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at village Kambhi, District Palwal(Under Mahagram Yojna). { 13/11/2020 - 12/05/2022 } 6.53 RAJESH KADIYAN 28/10/2020
72 Palwal PHED No. 3 DPR for providing sewerage facility in village Bhiduki, Tehsil Hodel, Distt Palwal (Under Mahagram Yojna) Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible pumping set of 1000/1500 LPM, 15 mtr Head, providing, laying, jointing, cutting and testing of 200 mm to 500 mm i/d SWP sewer line and all other works contingent thereto. { 21/01/2021 - 20/07/2022 } 7.19 RAJESH KADIYAN 18/01/2021
73 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities and Sewage Treatment Plant at village Deeghot, District Palwal (Under Mahagram Yojna). { 13/11/2020 - 12/05/2022 } 8.51 Jasveer singh Contractor 28/10/2020
74 Palwal PHED No. 3 Detailed Project Report Providing Sewerage Facilities at village Aurangabad, District Palwal(Under Mahagram Yojna) Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible pumping set of 600/800 LPM and all other works contingent thereto. { 16/01/2021 - 15/07/2022 } 7.63 Jasveer singh Contractor 06/01/2021
75 Palwal PHED No. 3 Detailed Project Report for Providing Sewerage Facilities at village Sondhad, District Palwal(Under Mahagram Yojna).Construction of 2 No. IPS consisting with RCC collecting tank, pump chamber, boundary wall, supplying, erection, testing and Commissioning sewage submersible 2 No. pumping set of 700/500 LPM, 15 mtr Head, providing, laying, jointing, cutting, testing of 200 mm i/d DI Rising Main from and all other works contingent thereto. { 28/12/2020 - 27/06/2022 } 6.45 Jasveer singh Contractor 17/12/2020
76 Palwal PHED No. 3 Providing CIPP (Technology of existing sewer line of size 600 mm i/d from Old Sohna Road Wine Shop to City Thana and 1000mm i/d RCC pipe sewer line from Mangla Medical Store to Parshu Ram Colony and desilting of sewer by Super Sucker Machine in various places of Palwal Town, Distt Palwal { 05/07/2021 - 04/01/2022 } 6.46 V N ENGINEERING COMPANY 30/06/2021
77 Palwal PHED No. 3 Estimate for Providing CIPP (Cured in Place Pipe) Technology of existing sewer line of size 1200 mm i/d RCC pipe sewer line from Panchwati Chowk to near STP of Palwal Town and all other works contingent thereto in Palwal Town { 15/04/2022 - 14/10/2022 } 7.63 V N ENGINEERING COMPANY 07/04/2022
78 Palwal PHED No. 3 Providing Sewerage facilities in village Aurangabad, District Palwal under Mahagram Yojana/NABARD, “Design, construction, supply, erection, testing and Commissioning of 2.50 MLD MPS Comprising of receiving chamber, Mechanical Coarse Screen, Raw Effluent Sump cum Pump House, Pumping Machinery and all other works contingent thereto. { 28/01/2022 - 27/01/2023 } 5.42 Rajesh Kumar Contractor 19/01/2022
79 Palwal PHED No. 3 Providing Sewerage facilities in village Deeghot, District Palwal under Mahagram Yojana/NABARD, “Design, construction, supply, erection, testing and Commissioning of 2.50 MLD MPS Comprising of receiving chamber, Mechanical Coarse Screen, Raw Effluent Sump cum Pump House, Pumping Machinery, Mechanical Fine Screens, Detrius Chamber, 2.50 MLO STP and all other works contingent thereto. { 28/01/2022 - 27/01/2023 } 5.42 Rajesh Kumar Contractor 19/01/2022
80 Panipat PHED No. 2 Part – A Water Supply Augmentation of water supply scheme by changing old pipe lines in village Sewah Distt. Panipat Part – B Sewerage System Providing sewerage system in village Sewah Distt. panipat { 11/09/2019 - 10/03/2021 } 8.62 H S Construction Company 11/09/2019
81 Panipat PHED No. 2 PART-B- Providing sewerage system in village Chulkana Distt. Panipat. Laying of 21.44 km sewerage network of different sizes in village Chulkana, Distt. Panipat. Operation and maintenance of Sewerage Scheme for 5 years { 24/12/2020 - 23/06/2022 } 6.67 Jasveer singh Contractor 24/12/2020
82 Panipat PHED No. 2 PART-A- Sewerage System- Providing sewerage system in village Bapoli Distt. Panipat “Laying of 25.64 km sewerage network of different sizes in village Bapoli, Distt. Panipat. Operation and maintenance of Sewerage Scheme for 5 years after defect liability period of 1 year after trial run period of 3 months { 20/11/2020 - 19/05/2022 } 5.71 RAJESH KADIYAN 20/11/2020
83 Panipat PHED No. 2 Detailed Project Report For Shayama Prasad Mukherji Rurban Mission (Sewah Cluster) 9 Villages, District Panipat, “Providing, Installation of 6 tube wells upto 350m BGL, Construction of 6 tube well Chambers, boundry wall, laying of internal Distribution Pipe Lines, Supply, Erection, testing and commissioning of 6 submersible pumping sets for tube wells.... { 28/05/2020 - 27/11/2021 } 5.28 Nar singh Goel 21/05/2020
84 Punhana PHED Construction of 1 No. ranney well, installation of 8 No. t/well const. of main boosting station in village Sultanpur and pumping machinery, independent feeder for ranney well and MBS Sultanpur { 25/07/2021 - 24/01/2023 } 31.28 Advanced Infratech Pvt. Ltd 07/07/2021
85 Punhana PHED P/F pumping machinery, Providing and fixing of DG set, transformer at Main Boosting Station Uttawar, laying, jointing, testing and commissioning of 800 mm i/d DI Rising Main from MBS Sultanpur to MBS Uttawar, Construction of 07 no. steel truss bridge for various spans for crossing of Agra Canal, crossing of railway line, crossing of national highway with 3 months trial run period after commissioing { 12/02/2022 - 11/02/2023 } 17.58 Chahar Construction Co. 02/02/2022
86 Punhana PHED Providing and fixing of pumping machinery, providing and fixing of DG set, transformer at Main Boosting Station Bhadas, laying, jointing, testing and commissioning of Main 800 mm i/d DI rising main from MBS Kot Bahin to MBS Bhadas and 300, 350 and 400 mm i/d DI Sub Rising Main from MBS Bhadas to IBS Umra, Jalalpur, Bhadas, Nagina and Khanpur Ghati (upto Junction point) { 18/02/2022 - 17/02/2023 } 14.92 Chahar Construction Co. 10/02/2022
87 Rewari PHED No. 1 Ibrahimpur, providing canal based water works gr. of 17 No. villages { 01/11/2018 - 30/10/2019 } 11.7 Jai Shree Balaji Const Co. Panipat. 29/10/2018
88 Rohtak PHED No. 2 Augmentation of Water Supply Scheme Nindana, “Design, testing , commissioning of automated PLC controlled SCADA based water purfication plant of 3 MLD capacity Part-B Sewerage system in Nindana ` construction of 2 no. intermediate pumping station consisting of 2 no. collecting tanks including screening chamber,inlet box, Operation and mtc. of 5 years for water supply including WTP`s and sewerage after defect liability period for 12 months { 09/09/2019 - 08/03/2021 } 9.5 Kulbir Singh 05/09/2019
89 Rohtak PHED No. 2 Nindana- construction of 2 no. intermediate pumping station consisting of 2 no. collecting tanks including screening chamber,inlet box, pump chambers over the collecting tank, supplying and installation of pumping machinery at the intermediate pumping station, supply , laying jointing and testing of stone ware pipes of size from 100 mm to 400 mm , construction of brick masonry manhole chamber, providing SFRC manhole covers and frames { 09/09/2019 - 08/03/2021 } 6.53 Kulbir Singh 05/09/2019
90 Sirsa PHED No. 2 Designing, Const, Testing, Commissioning, O and M for 5 years after defect liability period of 12 months after 3 months successful trial run of Channel, 2 Nos. S/S Tanks, 25MLD Automated WTP , 1 No. CWT, SCADA system and all other electrical, mechanical, instrumentation and other works contingent there to complete in all respects on Turnkey basis at Village Panjuana, Sirsa Town, Haryana.” { 07/12/2017 - 06/03/2019 } 23.9 M/S Ashok Kumar Jain, Govt. Contractor 01/12/2017
91 Sirsa PHED No. 2 Laying of D.I. Rising Main from Canal to Main Water Works, Construction of One No. Pump Chamber of size 10`x12`-1 No., Generator Set 500 KVA-1 No. with Platform - 1 No., Transformer with Plateform - 1 No., Electric Meter Room-1 No., reconstruction / repairing of Boundary Wall, C.C. Road and Plinth Protection, Laying of 300mm dia D.I. Pipe Line at Mini-Sectt Water Works area and all other works contingent thereto { 10/12/2019 - 09/06/2021 } 8.5 Jai Parkash Garg 27/11/2019
92 Siwani PHED Augmentation of water supply scheme Loharu Town by Providing canal based water works, Distt. Bhiwani, { 21/09/2020 - 20/03/2022 } 21.46 Shree Balaji Builders 11/09/2020
93 Siwani PHED Barwa vill Aug. WS scheme, `Const. of 1 RW P/Station, 1 WW, const. testing and comm.of 2.50 MLD automated PLC based WTP, SandS tank, CWT, PC, B/Wall, CC road, RW and CW RM lines, laying of dist. and prov. FHTC, supply, erection and comm. of RW and CW pumping sets, electric transformers and DG sets of required capacity, OandM for 12 M during def. liab.period after trail run of 3 months and 5Y thereafter and all other works conti. thereto { 01/05/2022 - 30/04/2024 } 9.39 Jasveer singh Contractor 13/04/2022
94 Siwani PHED Barwa Part B- Sewerage system- Providing sewerage facilities and STP at village Barwa, Distt. Bhiwani, “laying of pipe sewerage network of different sizes and OandM for 12 months during defect liability period after trial run of 3 months and 5 years thereafter and all other works contingent thereto” { 01/05/2022 - 30/04/2024 } 7.26 Jasveer singh Contractor 13/04/2022
95 Siwani PHED Upgradation and automation of existing gaseous chlo. system and inst. of online monitoring system for TandC in PHED Siwani, `Designing, P,F testing and comm. of online analyzer for TandC, auto switchover, ch. dry scrubber and auto off valves and all other works cont. thereto at various WW and comp. Mtc. period of five years after three months TR period and one yer defect liability period complete in all respect { 17/05/2021 - 16/11/2021 } 6.8 GOYAL CONSTRUCTION COMPANY 10/05/2021
96 Sohna PHED Design and Construction of Pumping Station, 1 No Collecting Tank, RCC Screening C/Pump Chamber, B.Wall, Providing and fixing Non Clog Sewage Submersible Pump Sets , Providing, Laying, Jointing, Cutting, Testing, Commissioning 200 mm, 250 mm, 300 mm, 400 mm S.W. Pipe sewer, Construction of in balance approved colonies in Sohna Town Distt. Gurugram, Haryana.`` (UNDER NCRPB) { 16/07/2018 - 15/10/2019 } 10.47 Jain Construction Co. Hisar M/S 02/07/2018
97 Sohna PHED Prov. sewerage scheme and const. of Sewerage Treatement Plant for H.Mandi Town of Distt. Gurugram `Designing, const., erection, testing and commissioning of automatic and PLC controlled with SCADA 5.50 MLD main P/station, Rising main upto STP, const. of automatic and PLC controlled with SCADA 5.50 MLD Sewerage Treatment Plant based on Sequential Batch Reactor (SBR) Technology, including 700mm i/d RCC pipe effluent channel.(under State Plan.) { 09/12/2016 - 09/06/2018 } 7.5 SCC EICPL (JV M/s SHiv Const. Co. and M/s Enviro Infra Engineer Co.Ltd. 2120 U.E Jind) 05/12/2016
98 Sohna PHED Aug. Drinking W/S Scheme in Fluoride Affected 23 No. villages of Sohna Distt. Gurgram. `Supply and Erection of P/M at MBS Dudhola, laying of rising main from MBS Dudhola to IBS Ghangola, construction of IBS at Ghanghola, laying of sub rising main from IBS Ghanghola to village SBS, construction of 23 Nos. (Volume- I-II) { 27/07/2018 - 26/07/2019 } 7.19 Rajender Contractor, Punhana (Mewat) 13/07/2018
99 Sohna PHED Sohna Town and Rozeka Meo Aug. W/S scheme Design, const. andcommissioning of raw water pumping station at Budhera andrising main of PSC pipe line on turenkey basis comprasing ofinnelt channel, 2 no. S/S tank pump house, pumping machinery , including electrilcal, mechnical instrumentation works .Boundarywall, stff qtr,PSC pipe line, , surge control devices op. and maintaince for 3 years after defect liablity period of1 year { 01/02/2016 - 01/05/2016 } 27.39 Jain Const.Co.M/s 03/12/2009
100 Sohna PHED Design, Const.,erection , testing and commissioning , operation and Maintenance for 3 year after defect liability period of 12 months of canel based W/S Sch. for Sohna Town comprising of 2 Nos. storage and laying and testing of 600mm i/d, 450mm i/d , 300mm i/d DI Pipe Raising main upto Sohna Town and Rojka Meo , and all other works contingent thereto.(under NCRPB) { 01/02/2016 - 01/05/2016 } 18.81 Jain Cons. Company M/S 31/08/2009
101 Sonipat PHED No. 2 Aug.of sewerage Treatment plant work under NRCP at Sonipat `construction of New 25 MLD STP and repair of 30 MLD STP { 01/09/2013 - 31/05/2015 } 38 H.L. Handa 16/08/2013
102 Tohana PHED Providing, Laying, Jointing, Testing of SW pipe sewer and construction of manhole chambers at Jakhal Mandi Tehsil Tohana Distt. Fatehabad and all other works contingent thereto. { 15/07/2020 - 14/01/2022 } 6.85 OmParkash Contt. Berla 06/06/2020
103 Tohana PHED Providing sewerage scheme and Construction of Sewage Treatment Plant including Operation and Maintenance for 12 months during defect liability period after trail run of 3 months and Five years thereafter at Tohana Town of District Fatehabad ” { 15/10/2020 - 14/04/2022 } 5.79 M/s Shiv Construction Company Jind 25/09/2020
104 Yamuna Nagar PHED No. 1 DPR for designing of rising main from 20MLD STP MPS at Badhi Majra and 24MLD STP at Parwalon at Yamuna Nagar. `Design, construction, erection, testing and commissioning of rising main from 20 (10 plus 10) MLD STP at Badhri Majra nd 24MLD STP Parwalon, Yamuna Nagar, Pumping Station and Rising Main for safe disposal in River Yamuna near Udhri village, Yamuna Nagar and including operation and maintenance for 5 years. { 30/05/2019 - 28/05/2020 } 18.24 Jain Irrigation Systems Limited 27/05/2019
105 Yamuna Nagar PHED No. 1 Construction of Sewerage Treatment Plant and Sewerage Network in Saraswati Nagar (Mustafabad) Distt. Yamuna Nagar (Hon’ble C.M. Announcement). { 26/09/2017 - 25/09/2019 } 5.46 Inderjeet Singh Contractor 26/09/2017
106 Yamuna Nagar PHED No. 2 Prov.Sew. facilities to 7 Nos. villages i.e. Aurangabad, Ishopur, Patashgarh, Mandebri, Panjeton Ka Majra, Heri Rangran, Sasoli in MC Y.Nagar (Under CM Announcement No. 10054), SW and RCC NP-3 Pipe Sewer of size 200mm, 250mm, 300mm, 400mm, 500mm, 600mm and 700mm in village Sasoli, Kheri Rangran, Panjeton Ka Majra and Mandebari, { 25/07/2017 - 24/07/2019 } 6.14 Sh. Anil Deswal 11/07/2017
×